Table Hy07: Repair Costs of Unsafe Big River Mine Dams
Table Hy07: Repair Costs of Unsafe Big River Mine Dams
| Dam Name | Dam Height(ft.) | Storage(acre-feet) | MineWaste | Renovation Cost ($) * |
|---|---|---|---|---|
| St. Joe | 134 | 6,100 | lead | 14,000,000 |
| Leadwood | 60 | 1,000 | lead | 1,500,000 |
| Desloge | 40 | 3,000 | lead | 12,400,000 |
| Eaton | 30 | 4,500 | lead | 1,300,000 |
| EastBonne Terre | 40 | 3,000 | lead | 4,300,000 |
| Blackwell Mine | 87 | 4,000 | barite | 10,300,000 |
| Dresser #10 | 107 | 1,100 | barite | 2,700,000 |
| Old Mines | 61 | 1,200 | barite | 1,800,000 |
| Cadet #2 | 77 | 650 | barite | 6,000,000 |
| Richwoods B | 48 | 1,750 | barite | 2,600,000 |
| Cadet Mine | 96 | 950 | barite | 600,000 |
| Esbaugh-Martin | 115 | 650 | barite | - |
| DeSoto Mine A | 76 | 3,700 | barite | 5,800,000 |
| Kingston #1(Pfizer) | 85 | 1,700 | barite | - |
| Moeckel | 85 | 2,400 | barite | - |
| Dresser #11 | 100 | 600 | barite | 3,900,000 |
| Big Four Mine | 71 | 2,000 | barite | 600,000 |
* USCOE estimates, 1981
Content tagged with
Shortened URL
http://mdc.mo.gov/node/12222